Best Practices Manual

4.4 Rain Screens: Bottom of Wall
Rain Screen Bottom of Wall Detail | Hammer& Hand
A. WRB (WATER-RESISTIVE BARRIER)
B. FURRING
C. COR-A-VENT SV-5
D. WATER TABLE
E. FLASHING
F. CLADDING
Rain Screen Detail 1 Layer on WRB | Hammer & Hand
  • Layer on WRB.
  • Seal sheathing to stem wall with Joint & Seam filler.
Rain Screen Detail 2 Install Vertical Furring Strips | Hammer & Hand
  • Install vertical furring to correspond with the framing method (aligned with vertical framing members).
  • Use untreated 1×4 furring.
Rain Screen Detail 3 Attach Strip of Cor-A-Vent SV-5 | Hammer & Hand
  • Attach a continuous strip of Cor-A-Vent SV-5 insect blocker at bottom of furring.
Rain Screen Detail 4 Attach Water Table | Hammer & Hand
  • Attach water table to furring.
Rain Screen Detail 5 Install Flashing Above Water Table | Hammer & Hand
  • Install flashing above water table.
Rain Screen Detail 6 Install Siding | Hammer & Hand
  • Install siding to complete the rain screen.

 

Continue to 4.5 Rain Screens: Gable End >>>

creative-commons
Hammer & Hand’s Best Practices Manual is covered by a Creative Commons license that allows for redistribution, commercial and non-commercial, as long as content is passed along unchanged and in whole, with credit to Hammer & Hand. If any piece is shared online, it is required to credit Hammer & Hand and include a link to the relevant source page at https://hammerandhand.com/best-practices/manual/.